1.     BATCH ONE PROJECTS

a.     PROJECT STATUS SUMMARY

2015 was indeed a milestone year for CADIP which saw the successful completion of the two remaining Batch 1 projects namely; Mt Hagen New Terminal Building and Hoskins Upgrade. Mt Hagen Upgrade includes the construction of a new Terminal Building which comprises a Domestic and an International Terminal. Hoskins upgrade also saw the construction of a new Terminal building and the strengthening and extension of the existing aerodrome pavement and Runway.

Most CADIP Tranche 1 projects which includes Installation of new ILS equipment at PMIA, Supply and delivery of 3No Airport Fire Trucks to PMIA, Extension of PMIA Apron & Associated Works and Installation of Security fencing in Goroka, Hoskins, Gurney, Kavieng, and Wewak Airports were all completed and over to NAC in 2011 and 2013 respectively.

A summary of projects completed under Tranche 1 is as follows:

PROJECT

COMMENCEMENT DATE

COMPLETION DATE

COST

(PGK m)

Port Moresby Instrument Landing System (ILS)

Aug 2010

August 2011

2.73

Airport Security Fencing

 

 

 

Goroka

Dec 2012

Jun 2013

10.40

Hoskins

Sep 2013

Jul 2013

7.11

Gurney

Mar 2013

Sep 2013

9.50

Kavieng

Sep 2011

Mar 2012

7.20

Wewak

Feb 2013

Aug 2013

8.90

Port Moresby Domestic Apron Extension

Jun 2012

Sep 2013

40.90

Fire Truck Tenders (3) – Port Moresby Airport

Mar 2012

Mar2013

8.90

Hoskins Airport Upgrade

Jul 2013

Dec 2015

68.4

Mt. Hagen Airport Terminal

Jul 2013

Nov 2015

70.10

Figure 1. Newly constructed Mt Hagen (Kagamuga) Terminal Building

Figure 2. Hoskins Newly constructed Terminal Building

Figure 3. Hoskins newly constructed Taxiway

Figure 4. Before PMIA Domestic Apron Extension

Figure 5. After PMIA Domestic Apron Extension

Figure 6 Completed PMIA Domestic Apron Extension

Figure 7 Commissioning of PMIA Domestic Apron

 

2.   BATCH TWO PROJECTS

Following the successful passage of the Batch 2 Periodic Financing Request (PFR) in 2014 and consequent signing of the loan agreement during the final quarter of the same year, the CADIP-PIU has commenced and completed most prepatory works on the second batch of projects in and throughout 2015. Implementations of Batch 2 projects commenced in the second quarter of 2015 and are nearing completion.  The following is the list of projects scheduled under Batch 2:

CIVIL WORKS

(a)  GOROKA UPGRADE

Contract Name:

Goroka Airport – Aircraft Pavement Upgrading, New Terminal Building and Associated works

Contract No.:

CADIP-B2-10-2A1

Contractor:

China Overseas Engineering Group Co. Ltd (COVEC PNG)

Contractual Start Date:

07 January 2016

Original Time for Completion:

476 Days

Current Time for Completion:

476 Days

Contractual Completion Date:

27 April 2017

Airside works under this involves;

  • General Pavement Repairs;
  • 15m wide Patch Repairs to Taxiway A;
  • 12m wide Patch Repairs to Runway;
  • Strengthening of existing Aircraft Pavements;
  • Reconstruction of existing Aircraft Pavements, Stop way, RESA;
  • Construction of Ramps;
  • 3.0m wide Light Duty Shoulders to Runway;
  • 3.0m wide Light Duty Shoulders to Taxiway A;
  • Resealing, Preparation of Runway Strip 150m wide;
  • Pavement Markings, Application of Fuel Resistant Membrane, Installation of Earthing Point;
  • Construction of Subsoil Drains;
  • Construction of Open Lined Drains, Construction of Culverts;
  • Airfield Lighting Works, Apron Flood Lights; and
  • Construction of Temporary Taxiway including temporary culverts.

Landside works involves

  • Construction of a Tractor Shed, Power House, Fire Station,
  • Upgrade and rerouting the existing airport perimeter road; and
  • Construction of a New Airport market.

Associated works includes

  • Supply, delivery and installation of Diesel Standby Generators, Tractors, Slashers and;
  • Supply, delivery and installation of Wind indicators.

Figure 8. Goroka Secondary Runway Construction

 

(b) GIRUA UPGRADE

Contract Name:

Aircraft Pavement Strengthening and Associated works at Girua Airport

Contract No.:

CADIP-B2-43-2A1

Contractor:

China harbour Engineering Company Ltd (CHEC PNG)

Contractual Start Date:

1st April 2015

Original Time for Completion:

452 Days

Current Time for Completion:

538 Days

Contractual Completion Date:

20th September 2016

Airside Works under this contract involves:

  • Extension of Runway;
  • General Pavement Repairs;
  • 12m wide central Patch Repairs to Runway;
  • Strengthening of existing Aircraft Pavements;
  • Widening of existing Taxiway including fillets;
  • Construction of 7.5m wide Shoulders to widened Taxiway;
  • Construction of 5.0m wide Shoulders to Apron;
  • Construction of 15m wide Temporary Taxiway including fillets and 2.0m wide Shoulders;
  • Preparation of Runway Strip 90m wide and Taxiway Strip;
  • Construction of Reinforced Concrete Parking Wheel Pads;
  • Pavement Markings, Application of Fuel Resistant Membrane & Installation of Earthing Point;
  • Construction of Open Unlined Drains, Construction of RCP Culvert beneath Taxiway;
  • Construction of CMP Culverts beneath Temporary Taxiway; and
  • Construction of Grated Drain.

Landside Works under this contact involves;

  • Refurbishment to the existing Terminal Building;
  • Construction of new Terminal building;
  • Construction of a new Tractor Shed as well as a Power House to facilitate for back-up power systems and;
  • Supply and Installation of Additional Fencing around the Runway Extension.

 

(c) CHIMBU AIRPORT UPGRADE

Contract Name:

Chimbu Airport – Pavement Strengthening & Associated Works

Contract No.:

CADIP-B2-12-2A1

Contractor:

Shorncliffe (1967) Ltd

Contractual Start Date:

31th March 2015

Original Time for Completion:

365 Days

Current Time for Completion:

365 Days

Contractual Completion Date:

31st March 2016

Airside works under this contract involves;

  • Strengthening of existing runway;
  • 12m wide repair on the runway;
  • 5.5m wide repair on the runway;
  • 3.8m repair on the edge of the Runway;
  • Preparing and Widening of Strip to 80m;
  •  Construction of new Grated and Open Lined (O.L.D) drains including subsoil drains; construct culvert connecting Grated Drain to O.L.D;
  • Repair and strengthening works on the Taxiway and Apron area, and
  • Replacing and Relocating of existing Windsock.

Landside works involves;

  • construction of new NAC ASO house, a new 4 bay tractor shed;
  • Refurbishment to existing Terminal building;
  • access road out the Flight Strip;
  • Environmental Mitigation and Drainage Improvement; and
  • Installation of Security Fencing.

Figure 9. Chimbu Airport Runway Construction

 

(d) VANIMO AIRPORT UPGRADE

Contract Name:

Pavement Strengthening & Associated Works at Vanimo Airport, SANDAUN Province

Contract No.:

CADIP-B2-23-2A1

Contractor:

Global Construction Ltd

Contractual Start Date:

10th March 2015

Original Time for Completion:

456 Days

Current Time for Completion:

479 Days

Contractual Completion Date:

1st July 2016

Airside works involves;

  • General Pavement Repairs;
  • 12m wide Patch Repairs to Taxiway & Runway;
  • Strengthening of existing Aircraft Pavements;
  • Construction of Full Strength Shoulders to Existing Runway;
  • Widening of existing Taxiway, Widening of Apron;
  • Construction of Half Strength Shoulders to Apron & Taxiway, Temporary taxiway;
  • Refurbishments to existing Open Unlined Drains & Construction of Culverts; and
  • Airfield Lighting works & Apron Flood Lights.

Landside involves;

  • Refurbishments to the existing Terminal building;
  • Construction of new Terminal Building;
  • Construction of a new Tractor Shed;
  • Refurbishments to NAC House;
  • Power House, with associated works and;
  • The supply, delivery and installation of standby generators, tractors and wind indicators.

Figure 10. Vanimo Airport Runway Sealing

 

(e) FENCING INSTALLATION AT MOMOTE AIRPORT

Contract Name:

Installation of Security Fencing & Associated Works at Momote Airport

Contract No.:

CADIP-B2-31-2B1

Contractor:

Kaulong Estate Ltd

Contractual Start Date:

02nd May 2016

Original Time for Completion:

180 Days

Current Time for Completion:

180 Days

Contractual Completion Date:

06th November 2016

Fencing Works under this contract involves;

  • Installation of Hot Galvanized Palisade fence around the Perimeter of the Airport;
  • Replacing of existing drainage structures;
  • refurbishment to existing NAC Office building;
  • Construction of new H65 NAC ASO house;
  • Supply & Delivery of Kubota tractor including slasher;
  • Construction of 4 bay Tractor Shed;
  • Relocating and replacement of existing Windsock; and
  • Construction of a new access road.

 

(f) FENCING INSTALLATION AT BUKA AIRPORT

Contract Name:

Installation of Security Fencing & Associated Works at Buka Airport

Contract No.:

CADIP-B2-33-2B1

Contractor:

TBA

Contractual Start Date:

 July 2016

Original Time for Completion:

180 Days

Current Time for Completion:

180 Days

Contractual Completion Date:

 January 2017

Fencing Works under this contract involves;

  • Installation of Hot Galvanized Palisade fence around the Perimeter of the Airport;
  • Replacing of existing drainage structures;
  • refurbishment to existing NAC Office building;
  • Construction of new H65 NAC ASO house;
  • Supply & Delivery of Kubota tractor including slasher;
  • Construction of a new 4 bay Tractor Shed; and
  • Relocating and construction of a new Perimeter access road.

 

PROCUREMENT OF GOODS

(g) Supply and Delivery 9 x Fire Trucks

Contract Name:

Procurement Of Aircraft Rescue & Fire Fighting Vehicles Associated Equipment & Training

Contract No.:

CADIP-B2-15/22/30/21/20/10-2D1

Contractor:

Oshkosh Corporation, USA

Contractual Start Date:

04thNovember 2014

Original Time for Completion:

730Days

Current Time for Completion:

730 Days

Contractual Completion Date:

03rd November 2016

Procurement under This contract involves;

  • Six (6) new 4x4 Airport Rescue & Fire Fighting Vehicles (ARFF) 2 each to Mt Hagen, Nadzab and Tokua Airports;
  • Three (3) new 4x4 Airport Rescue & Fire Fighting Vehicles (ARFF) to Madang and Goroka airports;
  • Supply and Delivery to Mt Hagen, Nadzab and Tokua sites, three (3) fully equipped Support vehicles;
  • Training programmes and training aids for Fire Fighters; and

Refurbishments to Mt Hagen, Nadzab and Tokua existing Fire Stations.

Figure 11. New RFF Trucks for Mt Hagen and Nadzab Airports

 

(h)   PROCUREMENT OF CNS/ATM EQUIPMENTS

Contract Name:

Procurement of VHF Radio Aeronautical Communication System & Associated Works

Contract No.:

CADIP-B2-42/22/21/10/15/30/45/20/31-2B1

Contractor:

ST Electronics

Contractual Start Date:

TBA

Original Time for Completion:

365 Days

Current Time for Completion:

365 Days

Contractual Completion Date:

TBA

Procurement under this contract involves;

  • Supplying, Installing & Commissioning of duplicated VHF Radio equipment sets including all ancillary, Automatic Terminal Service systems (ATIS) and equipments, Fully redundant Terrestrial IP Local Area Network (LAN), Power Supply Systems including all associated equipments, Remote Control & Monitoring systems, communication equipments and Equipments Shelters for various sites;
  • Decommissioning and Transporting back of all old and unused systems, equipments, cables and associated facilities to PNGASL Headquarter; and
  • Training of PNGASL staffs.

Contract Name:

Procurement of Secondary Surveillance Radar System & Associated Works

Contract No.:

CADIP-B2-42-2D1

Contractor:

Indra Australia Pty Ltd

Contractual Start Date:

TBA

Original Time for Completion:

365 Days

Current Time for Completion:

365 Days

Contractual Completion Date:

TBA

Procurement under this contract involves;

  • Developing, supplying, installing and commissioning of new enhanced SSR Radar at PNGASL site;
  • Replacing existing radar equipment including the antenna and sub-stations at the radar site with new SSR systems;
  • Developing, supplying, installing and commission a Radar Test Bed at the radar site;
  • Providing PNGASL with all Support Equipments to maintain the new SSR; and
  • Upgrading and providing infrastructures at site including; Electrical Systems, Mechanical Systems, conduct maintenance and communications Radio link.
  • Decommissioning, removing and decomposing of obsolete or replaced systems and equipments; and
  • Developing, supplying, installing and commission of the new SSR system including all associated accessories, programs and systems.

Contract Name:

Procurement of HF Radio Aeronautical Communication System & Associated Works

Contract No.:

CADIP-B2-22-2D1

Contractor:

Indra Australia Pty Ltd

Contractual Start Date:

TBA

Original Time for Completion:

365 Days

Current Time for Completion:

365 Days

Contractual Completion Date:

TBA

Procurement under this contract involves;

  • Installation of all new  HF Radio Communication system to replace and enhance the availability, performance, reliability and provide effective HF communication coverage for PNGASL and;
  • Design, Supply, Installation and commissioning of all HF elements including HF Receivers, HF Transmitters, Integrated HF Communication Control Systems, HF Antenna Systems, HF Equipment Electrical (power supply), HF Maintenance Support and Remote control & Monitoring system, Logical and physical communication network for HF system elements on PNGASL WAN and HF equipment building including all associated installations.

 

(i)      Supply and Delivery of Fencing Material to Buka & Momote Airports

Contract Name:

Supply of Fencing Materials for Momote Airport & Buka Airport

Contract No.:

CADIP-B2-31/33-2C1

Contractor:

Markham Culverts Ltd

Contractual Start Date:

14th March 2016

Original Time for Completion:

90 Days

Current Time for Completion:

90 Days

Contractual Completion Date:

13th June 2016

BATCH 2 PHYSICAL PROGRESS TOWARDS THE END OF QUARTER 2/2016 IS AS FOLLOWS

COMPONENT

INDICATOR

PYSICAL PROGRESS

CIVIL WORKS

Vanimo Pavement Strengthening

Contract Awarded and Work Commenced

59% Complete

Girua Airport Upgrade

Contract Awarded and Work Commenced

Pavement strengthening 100% complete. New Terminal Building 5%

Chimbu Pavement Strengthening

Contract Awarded& Work Commenced

85% Complete

Goroka Airport Upgrade

Contract Awarded & Work commenced

14% Complete

Installation of Security Fencing at  Momote Airport

Contract Awarded

Mobilization in Progress

Installation of Security Fencing at  Buka Airport

Evaluation in Progress

Calling of Bids currently in progress

GOODS

HF Radio Enhancement

Contract Awarded

0% Complete

Secondary Surveillance Radar Replacement

Contract Awarded

0% Complete

VHF Communications Improvement

Contract Awarded

0% Complete

Supply and Delivery of  6 x new Fire Trucks

Contract Awarded

100% Complete

Supply of Fencing Materials for Momote & Buka Airports

Contract Awarded

60% Complete

Standby Power Generators and Power System Upgrade

Bid Documentation in Progress

Call for Bids in Q3 2016

 

3.     BATCH 3 PROJECTS

The CADIP-PIU team has already begun preparations for the upcoming Batch 3 projects under the CADIP Multi Finance Facility (MFF). This will include bundling of the projects to make the projects more viable. Unlike the previous Tranches, Tranche 3 will be the most challenging as it will cover all nine remaining Airports within the remaining 2.5 years of CADIP.

Projects planned under Tranche 3 will include upgrades at Momote, Mendi, Mt. Hagen, Madang, Vanimo, Security Fencing (Kiunga, Tari and Kerema) Wewak, Gurney, Kavieng and Buka Airports. All minor projects will be implemented separately as they are under Asset Maintenance, Goods, Program Support and Capacity Development.

CADIP PIU has in fact commenced Batch 3 with the Invitation of Bids (IFB) for Momote Upgrade currently in progress. CADIP will also shortly issue IFB for the upgrade works at Mt Hagen (Kagamuga) Airport.

4.     CURRENT CADIP TENDER

  • Aircraft Pavement Upgrade, New Terminal Building and Associate Works at Momote Airport, Manus Province. Bidding Period 25th January, 2016 to 05th May, 2016

5.     UPCOMING CADIP TENDER

  • Aircraft Pavement Upgrade, New Air Traffic Control Tower and Associate Works at Mt. Hagen Airport, Western Highlands Province
  • Aircraft Pavement Rehabilitation, New Terminal Building and Associate Works at Mendi Airport, Southern Highlands Province
  • Aircraft Pavement Rehabilitation, New Terminal Building and Associate Works at Mendi Airport, Southern Highlands Province
  • Runway Extension and Associate Works at Vanimo Airport, Sundaun Province
  • Aircraft Pavement Strengthening, New Terminal Building and Associate Works at Madang Airport, Madang Province
  • Security Fencing and Associate Works at Kerema, Kiunga and Tari Airports
  • Runway Extension, New Terminal Building and Associate Works at Wewak Airport, East Sepik Province
  • Aircraft Pavement Upgrading and Associate Works at Kavieng Airport, New Ireland Province
  • Aircraft Pavement Upgrading, New Terminal Building and Associate Works at Buka Airport, Autonomous Region of Bougainville
  • Runway Extension, Terminal Building Extension and Associate Works at Gurney Airport, Milne Bay Province